Vol. 25 No. 1 PROJECT COST CASE STUDIES
The costs for the following three case studies are from projects that IVI has monitored on behalf of lending institutions.
January 2010
 
Condominium
Condominium
Project Description
Size 11 stories, 352,000 SFG with 235 units
Site 2 acres
Location Washington, DC
Project Cost Synopsis
Development Rounded Cost Cost
Per SF
Land 19,317,000 55
Direct 53,352,000 151
*Indirect 19,317,000 55
Total 91,986,000 261
Cost Distribution
Graph: Land 21%; Indirect 21% Direct 58%
 
Full Service Hotel
Full Service Hotel
Project Description
Size 7 stories, 140,000 SFG with 200 guestrooms
Site 7 acres
Location Washington, DC
Project Cost Synopsis
Development Rounded Cost Cost
Per SF
Land 7,381,000 53
Direct 42,440,000 303
*Indirect 11,686,000 83
Total 61,507,000 439
Cost Distribution
Graph: Land 12%; Indirect 19% Direct 69%
 
Office Building
(Core and Shell)
Office Building
Project Description
Size 11 stories, 478,000 SFG
Site 3 acres
Location Washington, DC
Project Cost Synopsis
Development Rounded Cost Cost
Per SF
Land 26,637,000 56
Direct 59,932,000 125
*Indirect 46,614,000 98
Total 133,183,000 279
Cost Distribution
Graph: Land 20%; Indirect 35% Direct 45%

*Typical indirect costs include:

Survey Fees

EIS Report and Consultant Studies

Appraisal

Environmental Site Assessment Studies

Testing and Inspection Fees

Developer's Legal Fees, Approvals, and Financing

Title Insurance

Utility Connection Fees

Building Permit Fees

Mortgage Broker Fees

Leasing Fees and Commissions

Construction Financing Points

Mortgage Tax and Recording Fees

Construction Financing Interest


Accounting

Lender's Counsel

Lender's Construction Consultant

Real Estate Taxes

Auditing Costs

Builder's Risk Insurance

Developer's Fee

Interim Operating Costs


IVI News Brief
IVI Consults on Montage Resort Hotel & Residences Read More

Congratulations to the Winner of IVI's iPad Giveaway Read More